1011: FpML:ElectricityDelivery has unnamed type embedded within

July 19, 2010

closed

Major

Always

Schema

SteveTurner

mgratacos

Summary

FpML:ElectricityDeliverydelivery has untyped compleyType content:

... ....

This exists in FpML from at least version 4.6 This needs to be defined in a type, e.g. ElectricityDeliveryDeliveryConditions

Notes:

  • mgratacos

    07/27/10 7:35 am

    A new ElectricityDeliveryType has been added which includes the untyped content:





    Indicates under what condtitions the Parties’ delivery obligations apply.




    If present and set to true, indicates that delivery or receipt of the electricity may be interrupted for any reason or for no reason, without liability on the part of either Party. This element should never have a value of false.




    Indicates that the electricity is intended to be supplied from the owned or controlled generation or pre-existing purchased power assets of the system specified.




    Indicates that the electricity is intended to be supplied from a generation asset which can optionally be specified.