The complex type EquitySchedule is not used in the FpML Schema. It remains in fpml-eq-shared, and has a rule around it.

fpml-eq-shared.xsd(270):

Notes:

  • matthew

    08/22/07 7:27 pm

    Should the rule instead be on the AveragingSchedule?

  • matthew

    08/22/07 7:28 pm

    Averaging Schedule:



    Method of generating a series of dates.
    Methode zur Generierung einer Reihe von Terminen.




    The averaging period start date.




    The averaging period end date.
    Letzter Tag eines Durchschnittszeitraums.




    The schedule frequency.
    Zahlungsfrequenz laut Zeitplan.




    The schedule frequency type
    Art der Zahlungsfrequenz laut Zeitplan.




    The schedule week number.
    Wochenzahl im Zeitplan.




    Day of the Week



  • matthew

    08/24/07 10:22 am

    —–Original Message—–
    From: Jim Brous [mailto:jbrous@metrosolutions.com]
    Sent: 24 August 2007 11:02
    To: eqdwg@fpml.org
    Cc: matthew@stickledown.com; ‘Simon Heinrich’; ‘Marc Gratacos’
    Subject: RE: FpML-EQD Meeting 1400 LDN Fri 24 Aug 2007 Fw: Validation Rules for Equity Derivatives

    Since I may not be able to join the meeting today, here are my comments on
    the two issues:

    ID=470:

    Because equityEffectiveDate is optional, rule eqd-23 should be
    changed to
    If equityEffectiveDate exists, equityEffectiveDate >=
    ../../tradeHeader/tradeDate

    ID=468:

    EquitySchedule is used and the rule should remain.
    See equityFeatures/barrier/barrierCap/schedule
    It is also used in barrierFloor, knockIn, and knockOut

    Best regards,
    Jim

    Jim Brous
    Managing Partner
    Metro Solutions LLC
    917.593.4195
    jbrous@metrosolutions.com

    http://www.metrosolutions.com

  • mgratacos

    08/24/07 1:19 pm

    EQDWG/VWG meeting 2007-08-24
    Agreed to remove EquitySchedule since it is an orphan.
    The rule should be on the AveragingSchedule as pointed by Matthew.

  • iyermakova

    08/24/07 7:07 pm

  • iyermakova

    08/24/07 7:11 pm

  • matthewdr

    05/02/08 6:16 pm

    The change is not in the repository.

    The rule in the 4-4-5 (LCWD) release said:

    Context: EquitySchedule (complex type)
    eqd-24 (Mandatory)
    startDate <= endDate " Please apply the EQDWG's decision.

  • iyermakova

    05/09/08 12:49 pm

    The eqd-24 rule has been corrected and committed to trunk – http://www.fpml.org/issues/view.php?id=468

  • matthewdr

    05/09/08 1:27 pm

    Accepting the resolution from Irina.