"FOLLOWING" |
- |
The non-business date will be adjusted to the first following day that is a business day
|
"FRN" |
- |
Per 2000 ISDA Definitions, Section 4.11. FRN Convention; Eurodollar Convention.
|
"MODFOLLOWING" |
- |
The non-business date will be adjusted to the first following day that is a business day unless that day falls in the next calendar month, in which case that date will be the first preceding day that is a business day.
|
"PRECEDING" |
- |
The non-business day will be adjusted to the first preceding day that is a business day.
|
"MODPRECEDING" |
- |
The non-business date will be adjusted to the first preceding day that is a business day unless that day falls in the previous calendar month, in which case that date will be the first following day that us a business day.
|
"NEAREST" |
- |
The non-business date will be adjusted to the nearest day that is a business day - i.e. if the non-business day falls on any day other than a Sunday or a Monday, it will be the first preceding day that is a business day, and will be the first following business day if it falls on a Sunday or a Monday.
|
"NONE" |
- |
The date will not be adjusted if it falls on a day that is not a business day.
|
"NotApplicable" |
- |
The date adjustments conventions are defined elsewhere, so it is not required to specify them here.
|